May 20, 2015
Contact Information:
Terex Cranes Global Marketing
Press & Public Relations
E-mail: info.cranes@terex.com
the right equipment for the job
Two Terex® all terrain cranes used in the construction of Metrorrey Line 3
ZWEIBRÜCKEN, May 20, 2015 – Since 1991, the Monterrey Metro (generally referred as Metrorrey) has been serving over 170 million passengers annually in Monterrey, Nuevo León, Mexico. Accommodating more than 480,000 passengers each day, which significantly reduces traffic congestion, this rapid-transit rail system runs partially underground and partially elevated to keep it independent of other traffic.
To continue to alleviate the traffic situation in the city, a third Metrorrey line is under construction. When completed, Line 3 will connect the Line 2 terminus at General Zaragoza northeast to Hospital Metropolitano. Its 26 trains and 9 stations are expected to serve an additional 280,000 passengers daily. A consortium of Alstom Mexicana, Constructora Garza Ponce and Constructora Moyeda, a leading construction company in northeast Mexico that specializes in the design and construction of civil works (particularly bridge) projects, was awarded the contract by the State of Nuevo León to construct the 7.5-km long elevated metro line.
Mobility and Capacity
According to Arturo Moyeda Morales, CEO of Constructora Moyeda S.A. de C.V., having this project in the heart of Monterrey offered crews some unique equipment challenges. Crews needed cranes with the capacity to erect U girders, as well as with the mobility to lift at one end of the job in the morning and then move a couple of kilometers during the day to erect in different locations in the evening.
Each U girder weighed 230 t, the heaviest precast pieces ever erected in Monterrey, and measured 37 m in length, 1.85 m in height and 5.2 m wide. The girders had to be placed to heights between 15-22 m.
“We chose to use two Terex all terrain cranes — an AC 350/6 and an AC 500-2 — because they had the capacity to lift the girders (350-t capacity and a 64-m main boom length for the AC 350/6, and 500-t capacity and a 56-m telescopic boom length for the AC 500-2),” said Moyeda, “and the cranes are roadable, needing only six flatbeds each to transport the counterweights. In addition, a crew of 12 people can set up the cranes in just three hours.
“Once a crane was moved,” continued Moyeda, “and we had the go-ahead from the transit authorities, a lift could be done in less than 30 minutes per girder. It was the right equipment for the job.”
To aid Constructora Moyeda with the project, Terex provided Moyeda and his crews with a specialized training session on the cranes before work began, as well as have provided a good working relationship and after-the-sale support to the company.
Site Restrictions
Another unique challenge that crews faced while working in the confined spaces of the Monterrey metropolitan area was that Line 3 was to be erected above highway bridges, over pedestrian bridges and between power lines. Existing traffic patterns, old drainage lines and main water lines were also factors the consortium had to consider as they planned for, prepped and executed the project plan.
The original project proposal required the use of a launching gantry; however in order to use this method of construction, it was imperative that the construction sequence was done consecutive from pier to pier. If one pier could not be constructed due to interference all erection would have had to be halted. To circumvent this issue, Moyeda and his crews used the Terex cranes to construct a viaduct, in different fronts at the same time, so maintaining the continuity with a launching gantry was not needed.
“Most of the lifts were done with minimal traffic interruptions and in very confined spaces, with a number of underground and aerial obstacles,” said Moyeda. “On top of those site conditions, we also had to keep our crews productive in the Monterrey weather conditions, where temperatures can reach 115° F in the summer.”
According to Metrorrey, Line 3 is due to be commissioned in August, 2015.
For more information about the cranes used, please follow the links: AC 500-2 and AC 350/6
About Constructora Moyeda
Constructora Moyeda was founded 40 years ago by Arturo Moyeda’ father. Today, the company has more than 800 employees and owns four Terex cranes — the AC 350/6 and the AC 500-2 used on this job, as well as two HC-275 crawler cranes. Moyeda noted that Constructora Moyeda had approximately 30 people erecting, and more than 600 people working in the company’s precast plant fabricating, working each day on the Metrorrey Line 3 project.
About Terex
Terex Corporation is a lifting and material handling solutions company reporting in five business segments: Aerial Work Platforms, Construction, Cranes, Material Handling & Port Solutions and Materials Processing. Terex manufactures a broad range of equipment serving customers in various industries, including the construction, infrastructure, manufacturing, shipping, transportation, refining, energy, utility, quarrying and mining industries. Terex offers financial products and services to assist in the acquisition of Terex equipment through Terex Financial Services. Terex uses its website (www.terex.com) and Facebook page (www.facebook.com/TerexCorporation) to make information available to its investors and the market.
Na manhã de 23 de novembro de 2015 a cerimônia foi realizada grandiosamente para a plataforma subterrânea de escavação modelo TWZ260 da XCMG que saiu da linha de montage. Tota
Como um mercado global de alta qualidade, o mercado americanotrouxe grandes desafios à China que entra no mercado de máquinas de construção. Como a vanguarda da maquinaria de c
Recentemente, camiões-gruas da XCMG adquiriram uma grande encomenda de mercado no exterior. Baseando-se no desempenho favorável e reputação de confiança, 31 unidades de camiõ
O início voltou e tudo parecia fresco. No início de 2018, os vários pedidos em massa dos guindastes de tipo torre foram celebrados na China, com um valor total mais de 100 milh
Copyright Notice 2002-2024 global-ce.com Construction Machinery Online. All rights reserved.
Address: Room 901, Building C, Ruipu Mansion, Hongjunying South Road No.15, Chaoyang District, Beijing.100107 P.R.China